Project Information
|
Stage
|
idea
|
Sector
|
idea
|
Geographical Focus
|
China
|
Location
|
Henan Province, Hebi City
|
Description of Project
|
Hebi Coal Mining Group plans to implement 7 surface wells in No. 6 coal mine for pre-mining extraction. At the same time, Hebi will construct a 2.5 MW CMM power plant that will utilize the extracted CMM. More power plants will be installed at a later date.
|
Instrumental Organizations
|
Texas Transportation Institute, U.S. Environmental Protection Agency
|
Emissions reductions:
(MTCO2E)
|
10 million m3 methane/year after project implemented
|
Results and Outcomes
|
This pre-feasibility study will identify further areas of project support needed. For the final phase of the project, $7.3 million USD in funding is required to install up to 22, 500-kW generators.
|